A project to connect Antarctica to the global fibre-optic network has moved a step closer to reality. A new feasibility study, conducted by Salience Consulting and Pioneer Consulting for Chile’s telecommunications regulator Subtel, has confirmed that a submarine fibre-optic cable linking the continent to the global data network is technically viable.
The study marks a significant milestone for Chile’s ambitions to establish a direct digital connection with Antarctica, which currently relies heavily on satellite communications. With scientific research generating increasingly large volumes of data, a high-capacity fibre connection could significantly improve the speed, reliability and capacity of communications between Antarctic research stations and the rest of the world.
Commissioned in February 2025, the study was financed by the Development Bank of Latin America and the Caribbean (CAF) and the Multilateral Cooperation Center for Development Finance (MCDF). Over more than a year, researchers from Salience Consulting and Pioneer Consulting assessed 55 Antarctic facilities and produced a final report of nearly 2,000 pages, examining the technical, economic and other considerations involved in developing the system.
Two possible configurations have emerged. The smaller option envisages a cable of approximately 1,600 kilometres connecting Punta Arenas and Puerto Williams in southern Chile to three Chilean Antarctic facilities. Its estimated investment cost is $370 million.
A more extensive configuration would span around 4,100 kilometres and feature nine landing points, potentially connecting research bases operated by five countries, including Chile, Argentina, Brazil, the United States and the United Kingdom. This option carries an estimated price tag of $621 million.
Beyond improving connectivity, the cable could also serve a scientific purpose. The study considers integrating SMART sensors into the fibre-optic infrastructure, enabling continuous monitoring of temperature, pressure and seismic activity along the seabed of the Drake Passage. This would effectively turn the cable itself into a scientific instrument, providing researchers with real-time environmental data.
The consultancies behind the study
The project brought together two consultancies with complementary expertise in telecommunications and subsea infrastructure. Dubai-headquartered Salience Consulting specialises in digital infrastructure and telecommunications advisory. Since its establishment, the firm has delivered more than 100 projects across the Middle East, Africa, Europe, Asia and the Americas.
US-based Pioneer Consulting focuses on submarine fibre-optic network development. The firm has completed more than 150 projects spanning every ocean and six continents, bringing specialist expertise in the planning and development of subsea cable systems.
The two consulting firms were selected following a competitive tender process in which four groups submitted proposals, including Deloitte. Their appointment builds on their respective experience in advising on major digital infrastructure projects and developing submarine cable networks.
The next steps
Despite the positive technical assessment, significant hurdles remain before construction can begin. Securing financing, obtaining political support from other Antarctic nations and addressing environmental and regulatory requirements will all be essential.
The feasibility study has been submitted to Chile’s Ministry of Foreign Affairs, with the Antarctic Policy Council expected to consider the findings and oversee international coordination. If approved, implementation could take approximately eight years.